phonelogo+234 8146561114 or +2347015391124

SINGLE LINE TO GROUND FAULT ANALYSIS IN 11KV DISTRIBUTION FEEDER
(a case study of ado Ekiti electrical power distribution district)

USER'S INSTRUCTIONS: The project work you are about to view is on "single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)". Please, sit back and study the below research material carefully. This project topic"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"have complete 5(five) Chapters. The complete Project Material/writeup include: Abstract + Introduction + etc + Literature Review + methodology + etc + Conclusion + Recommendation + References/Bibliography.Our aim of providing this"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"project research material is to reduce the stress of moving from one school library to another all in the name of searching for"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"research materials. We are not encouraging any form of plagiarism. This service is legal because, all institutions permit their students to read previous projects, books, articles or papers while developing their own works.


TITLE PAGE

 

BY

---
--/H2013/01430
DEPARTMENT OF ----
SCHOOL OF ---
INSTITUTE OF ---



APPROVAL PAGE

This is to certify that the research work,"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"by ---, Reg. No. --/H2007/01430 submitted in partial fulfillment of the requirement award of a Higher National Diploma on --- has been approved.

By
---                                                     . ---
Supervisor                                                  Head of Department.
Signature……………….                           Signature……………….        

……………………………….
---
External Invigilator



DEDICATION
This project is dedicated to Almighty God for his protection, kindness, strength over my life throughout the period and also to my --- for his financial support and moral care towards me.Also to my mentor --- for her academic advice she often gives to me. May Almighty God shield them from the peril of this world and bless their entire endeavour Amen.



ACKNOWLEDGEMENT

The successful completion of this project work could not have been a reality without the encouragement of my --- and other people. My immensely appreciation goes to my humble and able supervisor mr. --- for his kindness in supervising this project.
My warmest gratitude goes to my parents for their moral, spiritual and financial support throughout my study in this institution.
My appreciation goes to some of my lecturers among whom are Mr. ---, and Dr. ---. I also recognize the support of some of the staff of --- among whom are: The General Manager, Deputy General manager, the internal Auditor Mr. --- and the ---. Finally, my appreciation goes to my elder sister ---, my lovely friends mercy ---, ---, --- and many others who were quite helpful.


PROJECT DESCRIPTION: This work"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"research material is a complete and well researched project material strictly for academic purposes, which has been approved by different Lecturers from different higher institutions. We made Preliminary pages, Abstract and Chapter one of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"is to be ordered for. Happy viewing!!!


ABSTRACT

The aim of this research work is to carry out fault analysis of 11KV distribution power system. Electric power is an essential facilitator for sustainable development of the modern nation state. While Nigeria is reported to suffer from severe shortages of electric power the condition of some of its newer constitutional units are unknown. In this work, electric power infrastructure and energy availability is studied for Ado-Ekiti, the principal economic and political hub of Ekiti State. During the study, the condition of all relevant equipment for power distribution at the 11 kV level was assessed. Power availability was also considered by collecting necessary data that had to do with energy supplied, faults and other outages. It was discovered that the distribution lines were in a rather poor state with as many as 25% of the poles not meeting a condition of "goodness", 33% of cross-arms being broken or unsatisfactory, about 10% of the insulators defective and almost 40% of the span not complying with standards. Hence this work presents a research on fault analysis of Ado Ekiti distribution power system.
Keywords: Distribution System, Over-current, Feeder, Earth Fault, Differential Fault, Ring Main

TABLE OF CONTENTS

 TITLE PAGE

APPROVAL PAGE
DEDICATION
ACKNOWELDGEMENT
ABSTRACT
TABLE OF CONTENT

CHAPTER ONE

    1. INTRODUCTION
    2. BACKGROUND OF THE PROJECT
    3. PROBLEM STATEMENT
    4. OBJECTIVES OF THE PROJECT
    5. SCOPE OF THE PROJECT

CHAPTER TWO

LITERATURE REVIEW
2.0     LITERATURE REVIEW

2.1         ELEMENTS OF ELECTRIC POWER DISTRIBUTION

2.2     DISTRIBUTION SYSTEM

2.3      COMPONENTS OF ELECTRIC POWER DISTRIBUTION SYSTEM

2.4       DISTRIBUTION FAULTS
2.5           MOST LIKELY CAUSES OF FAULT ON H.T AND L.T OVERHEAD LINES
2.7      TYPES OF POWER SYSTEM PROTECTION
2.8    DIFFERENT TYPES OF POWER FAULTS
2.9     CAUSES OF ELECTRICAL FAULTS

2.10   EFFECTS OF ELECTRICAL FAULTS

CHAPTER THREE

3.0      METHOD

3.1      THE ADO- EKITI DISTRICT OF THE PHCN

3.2     STUDY PROCESS FOR ASSESSMENT

3.3        FAILURE RATE ANALYSIS

3.4   LOAD CURVE STUDIES

CHAPTER FOUR

4.0       RESULTS AND OBSERVATIONS OF THE FEEDER NETWORK IN THE ADO DISTRICT

4.1   ESTIMATION OF LOAD CURVES FOR THE ADO DISTRICT

4.2        ANALYSIS AND ASSESSMENT OF THE PERFORMANCE OF THE EPDS IN THE ADO DISTRICT

4.3     DISCUSSION

CHAPTER FIVE

    1. CONCLUSIONS
    2. RECOMMENDATION

5.3     REFERENCES


CHAPTER ONE

1.0                                               INTRODUCTION

1.1                                  BACKGROUND OF THE STUDY

The predominant factor distinguishing modern man from his ancestors is the ability to efficiently manage energy. In recent times electric power has become the most ubiquitous form of energy used for production, recreation, control and for carrying out most activities because of the ease with which it can be produced, transported and converted to various applications.
Distribution system is the largest portion of the electrical power system (Goran et al., 2008). It can be defined as the part of a power system that distributes power to various customers in ready-to-use form at their place of consumption (Ramesh et al., 2009). Distribution system is the medium through which electric power is conveyed in bulk from the power distribution station to the various end users (Adejumobi et al., 2012). It holds a very significant position in the power system since it is the main point of the link between bulk power and consumers (Gupta et al., 2013).
Ado Ekiti is an agrarian town in the southwestern part of Nigeria. The town lacks many infrastructures which is common in most of the developing countries. One of these infrastructures is the poor state of electric power distribution. Electric Power distribution system in Ado Ekiti is something of a major concern. There are more outages than uninterrupted power supply in most parts of the state all the year round.
It is a known fact that electricity plays a dominant role in the socioeconomic development of any community. In view of the foregoing, this project seeks to identify the problems militating against regular, good quality electric power supply in the Ado Business district of Ekiti-State with a view to proffering solutions and suggestions where necessary. This is to improve the socioeconomic life of Power Holding Company of Nigeria (PHCN)’s customers in the state. Given this unsatisfactory state of affairs and the lack of comprehensive studies to formally guide the development of electric power in the state, there is a dire need for an assessment of the Ekiti-state electric power distribution with a view to quantifying the availability of electric power and examining some of the physical factors that may contribute to the poor state of electric power infrastructure so that remedial suggestions may be proffered for improved system performance. It is in the light of this situation that this research has been conceived so as to provide useful information of the present condition from which rational and well-thought out improvements can be planned and implemented. Having analyzed the performance evaluation of Ado Ekiti power system, this paper provides all the expedient solutions to enhance reliability and availability of power supply in Ado Ekiti Power Distribution District.

    Research Problem

The main research objective addressed in this project is to carry out an assessment of the electric power distribution system in the Ado district of Ekiti-State with a view to identifying and quantifying important parameters that can provide concise description of the state of electric power.

Objectives of the Research

The objectives of this research study are:

  1. To collate relevant information about the physical conditions of the electric power distribution system in the Ado district of Ekiti-State.
  2. To create a database of faults experienced between 2001 and 2009 on the distribution network in the district and to carry out an analysis of the faults.
  3. To study the quality of power and assesses the performance of the network between 2009 and 2010 by calculating useful indices of performance.

1.4                                                                                      SCOPE OF THE STUDY
The scope of this study covers assessing the condition of all relevant equipment for power distribution at the 11 kV level. Power availability was also considered by collecting necessary data that had to do with energy supplied, faults and other outages.

CHAPTER FIVE

Conclusions

In the course of this project an engineering assessment of the electric power distribution system in the Ado district of Ekiti-State has been carried out. The assessment aimed at investigating the physical state of the distribution system, operational performance of the system in terms of determining hours of power supply, hours of black-out, hours of load shedding, hours of fault as well as obtaining probabilities of consecutive hours of power at any time of the day.
From the results obtained in chapter four of this thesis, it is seen that on an annual average basis Ekiti-State is experiencing erratic power supply as power may only be available in about just a third of a year. This is evident in the fact that power may only be available for three consecutive hours for 101 days at 2.00a.m on the Bashiri feeder, the highest value for the four feeders. The low value is attributable to poor supply from source of power, periods of load shedding, periods of fault as a result of the poor state of the lines and other outages whether planned or unplanned.

Recommendations

The following recommendations are hereby advanced so as to improve system performance of power distribution in Ekiti-State:

      1. More attention should be paid to the maintenance of the distribution network by the Power Holding Company of Nigeria (PHCN).
      2. Government should vote more funds to infrastructural development of electric power distribution so that defective components can be replaced as soon as possible.
      3. The radial configuration of the distribution network should be replaced with a ring network so that power can be supplied from alternative sources.
      4. The right-of-ways should be adequately maintained in order to avoid interruptions on the network as a result of incidences of fallen trees and creepers. This will also make line tracing much easier.

 


CHAPTER TWO: The chapter one of this work has been displayed above. The complete chapter two of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"is also available. Order full work to download. Chapter two of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"consists of the literature review. In this chapter all the related work on"design and construction of an arduino based public address system"was reviewed.

CHAPTER THREE: The complete chapter three of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"is available. Order full work to download. Chapter three of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"consists of the methodology. In this chapter all the method used in carrying out this work was discussed.

CHAPTER FOUR: The complete chapter four of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"is available. Order full work to download. Chapter four of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)"consists of all the test conducted during the work and the result gotten after the whole work

CHAPTER FIVE: The complete chapter five of"single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)" is available. Order full work to download. Chapter five of "single line to ground fault analysis in 11kv distribution feeder (a case study of ado ekiti electrical power distribution district)" consist of conclusion, recommendation and references.

CLICK HERE FOR MORE RELATED TOPICS/MATERIAL


To "DOWNLOAD" the complete material on this particular topic above click "HERE"

Do you want our Bank Accounts? please click HERE

To view other related topics click HERE

To "SUMMIT" new topic(s), develop a new topic OR you did not see your topic on our site but want to confirm the availiability of your topic click HERE

Do you want us to research your new topic? if yes, click "HERE"

Do you have any question concerning our post/services? click HERE for answers to your questions


For more information contact us through any of the following means:

Mobile No phonelogo:+2348146561114 or +2347015391124 [Mr. Innocent]

Email address emailus:engr4project@gmail.com

Watsapp No whatsapp.html :+2348146561114


COUNTRIES THAT FOUND OUR SERVICES USEFUL

Australia, Botswana, Canada, Europe, Ghana, Ireland, India, Kenya, Liberia, Malaysia, Namibia, New Zealand, Nigeria, Pakistan, Philippines, Singapore, Sierra Leone, South Africa, Uganda, United States, United Kindom, Zambia, Zimbabwe, etc
Support: +234 8146561114 or +2347015391124

Watsapp Nowhatsapp.html
:+2348146561114


E
mail Address emailus:engr4project@gmail.com


FOLLOW / VISIT US VIA:

tweeter instagram.htmlfacebook logomyyoutubelogo.html

Order Full Material(s)
Download Full Material(s)
Bank Accounts

Contact us

Hire a writer

Order/learn construction


View other related topics

Frequently asked questions(FAQ)
View more related topics
Format = microsoft word

Chapters = 1-5 chapters


Price: N3,000.

FOLLOW OR CONTACT US VIA:
facebook logomyyoutubelogo.html